Project Description

Project : Merekabentuk, Membina dan Menyiapkan Projek Lebuhraya Pantai Timur Fasa 1 Dari Karak ke Kuantan ke Sempadan Negeri Pahang/Terengganu ACWC Overlay Between KM125 to KM100 West Bound (Kuantan-KL)

Client: Lembaga Lebuhraya Malaysia
Main Contractor: MTD Construction Sdn Bhd
Contract Amount: RM697,000
Date of Commencement: 21th September 2006
Date of Completion: 31st March 2007
Project Duration: 6 Months